Summary:

Planning is the key to success on a project of this magnitude undertaken in such a small timeline window. NEMX replaced this 48” wide by 118-foot tall, 25-ton elevator including a number of steel member upgrades in a 12-day period.

The Challenge:

The time factor is the biggest challenge for this project. Project planning was paramount to complete this job in the time frame allowed. Utilizing hot work (welding, cutting with a grinder etc.) was the name of the game to get this plant back into service on time.

Why this bean processing client chose NEMX:

NEMX was chosen due to price, ability, reputation within the industry and timeline plan.

How NEMX Responded:

Scrutinizing the project to separate hot work and cold work and then prioritizing critical path actions was the solution to the challenge. By doing this we were able to provide the structural member upgrades and replace the elevator in a timely fashion. Overcoming the standard roadblocks that come under these types of projects our NEMX crew rose to the occasion working safely for long hours and over multiple shifts.

The Results:

The client was extremely satisfied with our mobilization and the quality in which we delivered the installation. Our dedication to our plan, safety and to the timeline won NEMX the respect and gratitude of our client.

 

After

After

Summary:

An end user in the dairy industry provided a project that required 11 case spirals, 2 food grade spirals, 1 KM of single lane overhead conveyance with merging, 6 KM of overhead box conveyor, moving of 3 robotic cells and the revitalization of the packaging departments ceilings.

The Challenge:

This was a moving target project, erect some conveyors and some spirals, move a robotic cell then re-vitalize the ceiling. Then repeat… Planning and end user communication was paramount.

Why the dairy client chose NEMX:

NEMX was chosen due to price, ability, reputation within the industry and timeline plan layout at bidding time.

How NEMX Responded:

We know that proper preparation, timely accurate troubleshooting and constant communication are the key to successes on these projects. Utilizing our knowledge of the conveyor systems and our advanced installation team skill set NEMX performed to the end users delight delivering a new system with minimal production interference.

The Results:

A happy end user that had increased production and provided NEMX with further work opportunities.

 

 

Summary:

This baking industry awarded their cookie stacking project to our conveyor manufacturing partners Storcan international. As NEMX is the boots on the ground, we were awarded the installation portion of this project.

The Challenge:

While all green field jobs are not the same, many have similarities. The challenges pertaining to these jobs are ensuring the team is on the same page, sorting out equipment skids so as to not take up valuable end user floor space and communication of the inevitable issues that arise with construction with the stakeholders clearly and in a timely manner.

Why the bakery client chose NEMX:

NEMX was chosen due to price, ability, reputation within the industry and timeline plan layout at bidding time.

How NEMX Responded:

We know that proper preparation, timely accurate troubleshooting and constant communication are the key to successes on these projects. Utilizing our knowledge of the conveyor system and our advanced installation team skill set, NEMX performed to the end users delight delivering a new system a day in advance with minimal production interference.

The Results:

A happy end user, a happy partner equals repeat business and increased productivity. It’s a win, win WIN!

Summary:

In the end this baking industry awarded this box conveyance system project to our conveyor manufacturing partners Storcan international. As NEMX is the boots on the ground, we were awarded the installation portion of this project.

The Challenge:

This projects scop was the removal of some current line shaft box conveyors, modification a few currently installed line shaft conveyors to accept new merging locations and installation of a new spiral as well as several overhead conveyors, including curves all of which was designed to take place over a 2-week Christmas shutdown. All conveyors other than the spiral were suspended from the ceiling to which the trusses were beyond the ISO panel roof which had to be precisely drilled and hermetically sealed once completed due to food safety concerns.

Why the bakery client chose NEMX:

NEMX was chosen due to price, ability, reputation within the industry and timeline plan layout at bidding time.

How NEMX Responded:

We know that proper preparation, timely accurate troubleshooting and constant communication are the key to successes on these projects. Utilizing our knowledge of the conveyor system and our advanced installation team skill set, NEMX performed to the end users delight delivering a new system on time and on budget.

The Results:

A happy end user, a happy partner equals repeat business and increased productivity. It is a win, win WIN!

Before

During

After

Summary:

Planning is the key to success on a project of this magnitude undertaken in such a small timeline window. NEMX replaced this 48” wide by 350-foot, 15-ton troughing belt conveyor including a new platform complete with 700’ of handrail in a 12-day window.

The Challenge:

The time factor is the biggest challenge for this project. Project planning was paramount to complete this job in the time frame allowed. Utilizing hot work (welding, cutting with a grinder etc.) was the name of the game to get this plant back into service on time.

All structural elements were pre-fabricated, painted and shipped from the NEMX shop for pre-assembly prior to the shutdown.

Why this client chose NEMX:

NEMX was chosen due to price, ability, reputation within the industry and timeline plan.

How NEMX Responded:

Critical path timeline attention was the solution to the challenge to ensure we were on track. Breaking this project down by the hour and sticking to the schedule was the only way forward as action 1 had to be completed before action 2 started.

NEMX rose to the challenge and delivered a fully functional conveyor on time and on budget.

The Results:

The client was extremely satisfied with our mobilization and the quality in which we delivered the installation. Our dedication to our plan, safety and to the timeline won NEMX the respect and gratitude of our client.